활용사례

[Bridge] Wichita 강가 보도교 시공단계별해석 (미국)
[Bridge] Wichita 강가 보도교 시공단계별해석 (미국)

Wichita’s Riverfront Footbridges

 

  • 포스트텐션 PSC 사장교의 시공단계별 해석

  • 3D 선형 비선형해석

  • 케이블 텐션닝의 최적화로 시공사의 공기를 단축

As part of Wichita riverfront development program, two cable-stayed pedestrian bridges are being constructed to extend the city cycle network and provide better access to the surrounding neighborhoods and business attractions. The bridges?contractor, Dondlinger & Sons Construction Co., Inc., retained Genesis Structures to analyze the staged erection process and prepare the erection manuals required for each of these complex cable-stayed bridge structures. Genesis Structures used LUSAS Bridge analysis software to carry-out numerous detailed 3D linear and nonlinear analyses of the bridges and their components to help minimize the number of steps in the cable tensioning process and reduce the Contractor’s time and labor.

Overview

The city of Wichita, Kansas, boasts a bike and pedestrian transportation system that covers more than 150km, much of which runs through parks and along its rivers. As part of its riverfront corridor improvement project, two new bridges spanning 320m and 240m will cross over the Arkansas and Little Arkansas Rivers respectively at the site of the “Keeper of the Plains,” a 45m high, raised, iconic Indian statue. The bridges connect Exploration Place, a modern, interactive science museum, with the culturally significant Mid-America All indian Center. Because of their location, the cable-stayed bridges incorporate tapered towers and a unique stay-cable configuration that mimic feather shapes and other patterns found in Native American headwear.

 

Bridge construction

Each bridge is comprised of a 120m high steel tower of 60″ triangular cross-section that supports precast concrete box segments that are initially built on falsework bents and then longitudinally post-tensioned together. 

Each tower is formed from two, 60 ton steel leg segments that are lifted into position using a specially designed lifting saddle and integral lifting lug. A 30 ton upper cable anchorage unit sits on the top of both tower legs. This anchorage was assembled at ground level for ease of installation of the bolted connections and then raised atop the legs using special rigging. Adjustments were made using a screw jack system to obtain the correct tower leg positions prior to final assembly. Partial penetration welds around the full perimeter of the upper ends of each leg and the unit secure it in place.

Decks are constructed of 32?long, hollow box segments having a maximum depth at the bridge centerline of 48″ and tapering to a 24″ visible profile. During assembly each segment is placed on steel falsework bents that allow longitudinal movement of the segments during placement and longitudinal post-tensioning. Ten inclined cable pairs support the longer span bridge deck and eight cable pairs support the shorter bridge. Main stay cables (provided by CBSI, Inc.) are 2″ diameter with back stay cables of 3 3/8″ diameter ASTM A586 Structural Strand.

 

Staged erection analysis

Analysis with LUSAS was required to model the complex erection sequence involving falsework construction in the river, post-tensioning of the precast concrete deck system, and sequential cable tensioning to lift the structure from its temporary supports to create the free-spanning cable-stayed spans.

Project specifications required that the bridge geometry be set-up at the beginning of its service life to obtain the target geometry after 10 years of service. To accomplish this, time-dependent effects due to creep and shrinkage in the post-tensioned concrete deck segments had to be evaluated. This was achieved by using the CEB-FIP 1990 creep and shrinkage material model in LUSAS.

After tower erection each of the 32m long deck box segments were constructed upon structural steel falsework bents and initially post-tensioned together for continuity using four, 1″ diameter post-tensioning bars. Following the complete longitudinal assembly of the segments, four 19 strand, 0.6″ diameter tendons were installed and tensioned to obtain the required compression in the deck system prior to cable installation. The LUSAS post-tensioning wizard was used to model the erection of the deck segments at each stage of the construction.

Preliminary tensioning of the stay cables in the LUSAS model was accomplished through initial strain loading of the nonlinear beam elements representing each cable. During the actual stay-cable installation, the longitudinal concrete deck system was to be lifted from its temporary supports through a carefully planned installation sequence. The falsework system was required to allow longitudinal movement and shortening of the deck system as well as unrestrained lift-off from the supports. Modeling for these effects was accomplished through the use of nonlinear joint element supports in LUSAS. Final tensioning of the stay cables was achieved by applying a negative temperature load to each cable pair to obtain the desire tension. Excellent correlation was obtained between LUSAS predicted cable tension values and on-site measurements.

3D solid modelling of box segments

Each of the box segments contained access openings in the top slab to provide access for the installation of the longitudinal post-tensioning system as well as for two tuned mass dampers (provided by Motioneering, Inc.) to control pedestrian-induced vibrations. Openings for the tuned mass dampers exceeded 15?in length and created areas of discontinuity in the top slab during lifting operations and longitudinal post-tensioning. To verify that each of these locations provided adequate continuity, individual segments were modelled using 3D solid elements and checked for both lifting stresses and longitudinal stresses due to post-tensioning.

3D modelling of tower

The unique tower design of these bridges creates a highly confined compression and flexural zone immediately below the upper cable anchorage. To ensure adequate stress transfer brought on by the cable tensioning, a 3D LUSAS model of the entire tower and upper cable support was developed to determine the local zone effects in this region. Confirmation of the local stresses was obtained prior to proceeding with the complete analysis.

“We used LUSAS Bridge exclusively for the erection engineering of the Wichita Bridges and obtained excellent correlation between the on-site cable stayed measurements and the values that LUSAS predicted for lift-off”

Dr. David Byers, President, Genesis Structures.

유사 사례

철도 배수구의 자동 설계

lusas_9170_2_culvert_geometry_300

[Bridge] 유리로 덮힌 Helix 교량의 해석 (영국)

1

[Bridge] BS5400에 따른 교량평가 (영국)

1

[Bridge] Store Baelt 동편 현수교의 해석

1

[Bridge] Plashet 학교의 (보행자용)인도교 교각의 설계

1

니믈부르크의 라베강 위에 있는 사장교

lusas_9180_2_labe_nymburk_complete_775

두바이 지하철 경량철도 프로젝트의 레일 트랙/구조 상호작용 해석

lusas_9185_2_dubai_metro_station_footbridge_775

휘틀 아치와 유리 교량, 코벤트리

lusas_9152_2_GlassBridge-MillenniumPlace-1_775

[Civil & Structural] 전주 월드컵 경기장(TGP,영국)

1

올림픽 공원 교량

lusas_9202_1_atkins_100

LPI 활용 기초 - 매크로 정의

LPI 란 ?

LUSAS Programmable Interfaace 를 의미하며,  반복적으로 수행하는 작업들에 대한 매크로를 정의하여 활용하는 것으로부터 LUSAS 를 플랫폼으로 하는 모델링, 해석, 설계검토, 도면작성 등의 전과정에 대한 자동화 프로그램 개발에도 활용할 수 있습니다.

작업 기록 개시

  • File > Script > Start Recording 

대화창에서 파일명을 지정하면, 이후 작업들이 VBS 혹은 JS 명령문 형태로 저장됩니다.

Line 1 개 정의

모델러에서 Line 1개을 정의해 봅니다.

작업 기록 종료

  • File > Script > Stop Recording 

기록을 종료합니다.

기록 내용 확인

아래와 같이 Line 을 정의하는 명령문 조합이 기록됩니다.

기록 내용 수정

아래와 같이 기록된 내용을 수정해 봅니다.
좌표를 변경시켜 가며, 총 10회 반복하도록 한 것입니다.

수정된 파일 실행

  • File > Script > Run Script 

수정된 파일을 실행시키면, 아래와 같이 10 개의 Line 이 작도 됩니다.